Anne’s Lane Water Main Replacement Project

The Anne’s Lane water main replacement project will begin Friday, July 21, 2017 with a pre-construction video at 8:00 AM. The week of July 24th Jamco Excavators will be digging test pits on the street to locate sewer lines. The water main construction will begin on July 31st.

 

All homes that receive their water from the Anne’s Lane water line now will be connected to an above ground temporary water line during the construction process.

 

If you have any questions please call the Seabrook Water Department at

474-9921. Our hours are from 7:00 AM – 3:00 PM, Mon. thru Fri.