The Seabrook Board of Selectmen authorized a study on climate resiliency at the Seabrook Wastewater Plant, which was unveiled on a recent visit to the Plant by Congressman Pappas. This project was funded by NOAA’s Office for Coastal Management in conjunction with New Hampshire Department of Environmental Services Coastal Program.
The goal of the study was, in the most basic terms, to identify the vulnerabilities of the plant to climate based sea level rise. We have also identified plant “hardening” measures that can be taken to mitigate the very real and severe challenges faced in the runup to 2050. The recommendations will inform Seabrook’s capital planning in the wastewater department.
I am appreciative of the work of Curtis Slayton, Sewer and Water Superintendent, and Daumanic Fucile, Chief Sewer Operator. My thanks to Weston and Sampson for their fine work on this project as well.
seabrook-wwtf-climate-resilience-assessment-project-report-july-2021